The bell cable serving the businesses directly east of the site will be relocated on June 26 at 2pm. Bell/Expertech will access the line on the pole in the delivery lane behind these businesses and we have been promised the work will proceed with no interruption to the phone service

The catch basin installation on Second Avenue has been delayed slightly. One lane of traffic on 2nd avenue will remain closed during this work.

Work pouring walls and formwork for second level slab continues. Backfill north side of property and remaining of underground services will take place Wednesday to Friday.

The main site access on Third Avenue remains a busy spot and pedestrians are asked to stay clear.

Please feel free to also contact the City Project Manager Rob Faris directly at 613 580 2424 ext 43063 or myself Peter Dodsworth at 613 580 2424 ext 44190