Notice of Construction Catherine at Kent St

Notice of Construction Catherine at Kent St

On behalf of the Combined Sewage Storage Tunnel project team, please find attached information regarding longer-term construction at the corner of Catherine St. and Kent St.

By way of background:  There was a public open house in May of 2017 at the McNabb Community Centre to provide information about planned construction at the corner of Catherine and Kent (as well as at McLeod and Kent). The City’s contractor is expected to mobilize at Site 9 in mid-August to set-up fencing and traffic control measures, with actual shaft construction beginning in early September.

Site 9 Construction Notice

2018-08-08T15:17:35+00:00 August 8th, 2018|News|Comments Off on Notice of Construction Catherine at Kent St